FEOC Effective Control: How Licensing and Supply Contracts Can Disqualify a BESS Project

Most diligence teams read the battery supply agreement and stop. The provisions that fail the test usually sit in documents they never open. The broader rules are covered in Carina’s FEOC compliance guide for BESS.

Under the One Big Beautiful Bill Act (OBBBA), any intellectual property (IP) license with an SFE entered into or modified on or after July 4, 2025 is treated as effective control, whatever its terms. The word that catches projects is “modified.” A license signed in 2023 and amended in 2026 to add a new product generation is a new arrangement for this purpose.

The diligence request to the integrator should cover:

  • The identity and ownership of every licensor whose technology is in the product
  • The execution date of each license and the date of every amendment
  • The royalty term and how royalties are calculated
  • Whether the licensor can direct the sourcing of components or critical minerals

An integrator that will not answer these questions has answered the most important one.

The statutory factors read abstractly. In battery storage they show up in specific documents.


Effective control factor

Where it appears in BESS

What to check
Authority over output, dispatch or who buys the outputEnergy management system (EMS) and plant controller agreements; optimization servicesWho sets the dispatch schedule, and whether the original equipment manufacturer (OEM) can override it remotely
Exclusive maintenance or operationsLong-term service agreement (LTSA); warranty terms; capacity maintenance agreementsWhether the warranty is void unless the OEM performs all maintenance
Restricted access to operating dataCloud monitoring platform terms; data ownership clausesWhether the owner gets raw cell-level data, or only what the OEM’s portal displays
Long royalties or control of sourcingTechnology licenses; augmentation supply termsRoyalties beyond 10 years; augmentation units that only the OEM can specify

Two patterns deserve attention. The first is warranty conditioning. A warranty that lapses unless the OEM performs all maintenance creates an exclusive maintenance arrangement in practice, even when the LTSA never uses the word “exclusive.”

The second is the power conversion system (PCS). The PCS manufacturer is often a different company from the cell maker and the integrator, with its own parent and its own licensing history. It needs its own ownership and licensing review.

For tax years beginning after July 4, 2027, the credit can be recaptured in full if, within 10 years of placed-in-service, the taxpayer makes a payment to an SFE under a contract that grants effective control. Diligence therefore has to follow money over time, not just signatures at closing.

A battery storage project makes payments to its supply chain for most of its life: LTSA fees, augmentation purchases in years 5 to 10, software subscription renewals and firmware update charges. Each one is a test date. A contract that is clean at commercial operation can stop being clean when:

  • A counterparty’s ownership changes and it becomes an SFE.
  • The LTSA is assigned to an affiliate with a different ownership chain.
  • A software license renews on new terms after July 4, 2025.

The working tool is a payment calendar. It lists every counterparty with a foreign ownership link, every recurring payment to it, and the date each payment falls due through the end of the recapture window.

Notice 2026-15 is interim guidance. Treasury has said proposed regulations are coming, and until they arrive, tax equity investors read effective control conservatively. They cover the remaining uncertainty with indemnities, holdbacks or price.

In diligence they ask for:

  • An inventory of every contract that touches operations (supply, EPC, O&M, warranty, software, data access, IP licenses), with an effective control review note on each
  • The ownership chain of every counterparty, the PCS manufacturer included
  • License execution and amendment dates
  • Supplier certifications and the cost allocation behind the MACR calculation
  • Confirmation that records will be kept for at least 6 years from the credit claim

The practical lesson is sequencing. Effective control problems found at supplier selection cost a substitution. Found at financial close, they cost the deal timeline. Found in year 7, they cost the credit.

Carina Energy is a boutique owner’s representative firm specializing in BESS permitting and development. If you’re reviewing supply, service or license agreements for FEOC exposure, learn more about our approach or get in touch to discuss your project.

Related reading

This field is for validation purposes and should be left unchanged.
Name(Required)

BESS Permitting Intelligence Delivered to Your Inbox
FEOC compliance, OEM moves, moratoriums, tariff developments, and other updates
This field is for validation purposes and should be left unchanged.
Name(Required)
No spam. Only actionable insights.

READ BY HUNDREDS OF BESS PLAYERS